Sanitary Sewer Rehab Work in May

The next phase of sanitary sewer rehab work is scheduled to occur between 5/8/2023 to 5/26/2023. Please click the following link to the Sanitary Rehab Phase Map for the locations where this work is schedule to occur. Residents in these locations should have already received a preliminary notice for the upcoming work on the front door. If any residents at these locations have not received a “1-week notice” on their front door, please call Mike Blasczyk at 832-396-1233 or Dale Rogers at 281-898-0636 with Insituform Technologies, LLC.

A second notice will be posted on the front door 24-hours before work begins. Residents within this phase should check their front door daily for the 24-hour notice.

While the Contractor will make their best efforts to stick to the tentative schedule, sometimes factors like weather and other circumstances may affect the schedule.